View a step-by-step breakdown of how the process works.
Day 1
- Protect flooring and carpets where necessary
- Survey the property to decide the routes for installing pipework
- Mark holes where the wood frame is being installed
- Drill and vacuum fixing holes for wood fixings (2-3 hours of loud noise)
- Diamond drill through walls and beams as required
- Fix wooden frame work
- Install pipework
- Remove floor protection
Day 2
- Protect flooring and carpets where necessary
- Carpenters attach battens to walls
- Pipes are attached to battens
- Fill pipework with water and pressure test
- Install seal at main entrance
- Install boxing covers to wood frame
- Make good boxing decorations
- Remove floor protection
Day 3/4
- Smoke alarms are fitted
- Install any remaining boxed covers to wood frame
- Gaps where pipes have gone through are sealed
- Inspect installation
- Correct any identified defects if identified
- Installation signed off by Clerk of Works