November 26, 2026
As work to deliver the next phase of the Kingshurst Village Centre regeneration project gathers pace, contractor Willmott Dixon has restarted its community newsletter to help keep residents informed about upcoming works and project progress.
Copies of the newsletter will be displayed on local noticeboards, including at Kingshurst Library, and distributed within the local community.
We are sharing a summary of the latest update below to help residents stay informed about key milestones and planned activities. Alternatively you can view the newsletter here.
Back on site
Work is due to restart on site in December 2026, with initial activities including site setup and essential tree works. Construction activities are expected to commence in January 2027 as work gets underway on the new Village Centre development.
The project will deliver a new community, health and retail building, new homes and associated infrastructure improvements. The new community hub will bring together services including health facilities, a library, community spaces, a café and local shops.
Planned works and temporary disruption
According to Willmott Dixon’s latest community newsletter:
- Site establishment and tree works are planned during December 2026.
- Construction activity is expected to begin from 11 January 2027.
- Drainage works on Over Green Drive are expected to start from 18 January 2027 and are anticipated to last around four weeks. A temporary road closure (between the junction of Silver Birch Road and Church Close) and diversion route will be in place during these works.
- Church Close will be closed to vehicle traffic during the construction period to enable the delivery of parking and highway improvements. Pedestrian access will be maintained.
Further activities during the first part of 2027 are expected to include piling works, foundation construction and utility diversions.
Meet the project team
Willmott Dixon will be holding a community drop-in event at Kingshurst Library on Tuesday 1 December, from 1pm to 5.30pm, where residents can meet the project team, learn more about the construction programme and ask questions about upcoming works.
Residents should look out for Willmott Dixon’s community newsletter, which is being delivered locally and displayed on community noticeboards.
We will also continue to share key project updates through Council communication channels as the regeneration programme progresses.
If you need to contact the Willmott Dixon site team directly, you can do so on 01675 467 666